Building the third floor
26 Jan - 06 Febr
2010
| After
cleaning up everything we were ready to build. In
2007 steel bar extensions were already made for
another
floor |
| The
same contractor and workers whom worked for us two
and a half years ago started to work on January
26th |
| They
built the iron bars into boxes made of wooden
sheets and filled them with a mixer of cement,
sand and
stones |
| After
one day the workers took off the wooden sheets and
left the pillars to dry. On Febr.6th all pillars
were
built |
| The
contractor and the workers worked very hard and
left for two weeks for a well deserved Vietnamese
new years
holiday | |